Pipeline
Pre-commissioning of a 120 km crude pipeline
Cleaning, gauging, hydrotesting and drying of a new 24" crude line ahead of first oil.
120 km
Pipeline
4 weeks
Schedule recovered
9
Test sections
Challenge
The problem on site
A hurricane delay compressed the pre-commissioning window from 10 weeks to 6.
Solution
What Halvard delivered
Parallel test sections and a second dewatering spread recovered four weeks without adding risk.
Location
Texas Gulf Coast, USA
Related equipment & services
Pipeline Engineering & Integrity
Design, construction support, pigging and integrity management.

Next project
Shallow-water platform maintenance & P&A support
Have a similar project in mind?
Tell us the scope, the standards and the timeline. We'll come back with a plan.
Start a conversation